Client: Network Rail

Programme: 3 Months (September 2020)

 

Objective:

The overall objective for the scheme was to undertake a Feasibility Study for Network Rail. The work included multi-discipline surveys for the site, including PAS128 Surveys and develop options to upgrade the existing Network Rail office accommodation in line with client requirements.

Key considerations for the optioneering works were:

  • Risk Management
  • Budgetary Constraints
  • Construction logistics
  • Operational logistics
  • Access
  • Environmental Impact
  • Sustainability

 

Deliverables

  • Topographical Survey
  • Ground Penetration Radar (GPR) Survey
  • CCTV Drainage Survey
  • Ground Investigation Works – Trial Pits, Windowless Samples and Contaminated Ground / Sample Testing
  • Dilapidation Survey
  • M&E and Load Monitoring Surveys
  • UXO Risk Assessment
  • Condition Assessment Report for the existing office accommodation building
  • Feasibility Report, with options for consideration by the client for the future design works