Case studies: Professional Services

Brentford to Southall “Golden Mile” Surveys

Professional Services Surveys

Project Value: £220k Project Commenced: October 2020 Project Completed: March 2021 Client: Network Rail   About the Project Network Rail is developing a scheme to create connectivity for a passenger service between the existing Southall Station and a proposed station called Brentford Golden Mile. The London Borough of Hounslow has ambitious regeneration plans for the historic ‘Golden Mile’ employment…

New Cross Gate Feasibility Study – Drainage Surveys

Professional Services Surveys

Project Value: £28k Project Commenced: Jan 2021 Project Completed: May 2021 Client: Network Rail   About the Project The New Cross Gate Site Office was built approx. 10 years ago and while not life expired, the original teams occupying the building (Thameslink & Hither Green Teams) no longer require the building. There was a requirement for Network Rail’s own S&T and VARS Teams to have their own office space…

Newhaven Flood Defence Scheme

Professional Services Surveys

Project Value: £10k Project Commenced: December 2020 Project Completed:  January 2021 Client: BCM Construction   About the Project The works described are part of the wider Newhaven Flood Alleviation Scheme, which is being delivered by the Environment Agency. As part of this new flood protection measures were required for the interface with Network Rail infrastructure. The new demountable flood…

CAPEX RRAP’s Installation Kent & Sussex – Possession Planning & Man.

Professional Services

Project Commenced: September 2018 Project Completed: March 2019 Client: Network Rail   About the Project The CAPEX Project consisted of multi-disciplinary Design, Assurance, Construction Delivery and Entry Into Service as part of Infrastructure upgrades in Kent and Sussex. The Scope included design and installation of a number of Road Rail Access Points. The design assurance process covered full discipline integration including P-Way,…

Milton Keynes Hospital Power Upgrade – Design Project Management

Professional Services

Project Value: £600k Project Commenced: November 2020 Project Completed: October 2021 Client: NHS Milton Keynes   About the Project Milton Keynes hospital required a full design and installation works to be undertaken for the upgrade of an existing substation. This includes a phased decommissioning of the existing 350kVA transformers and installing a new 500kVA generator, as well as increasing the footprint to accommodate the…

Thingley – Christian Malford Resilience Scheme

Professional Services Surveys

Project Value: £140k Project Commenced: June 2020 Project Completed: November 2020 Client: Network Rail   About the Project This scheme from Christian Malford to Thingley increases the resilience of the power feed from Thingley ATFS onto the overhead line system which is part of The Greater West (TGW). The scheme comprises two low-level cabled auto-transformer feeders (ATF) and two low-level cabled overhead contact system (OCS)…

3rd Party / Asset Protection (ASPRO) Schemes – Liverpool Street

Professional Services

Project Value: £12m Project Commenced: April 2020 Project Completed: May 2021 Client: MTR CrossRail   About the Project The delivery of ‘On-Network’ works by 3rd parties or other stakeholders via ‘Asset Protection’ (ASPRO) assurance processes are becoming an increasingly popular vehicle of delivery. This arrangement allows the 3rd party clients more control over the design and delivery of schemes, helping control cost and minimise scope…

Lyminster Bridges

Professional Services Temporary Works Design

Project Value: £3.6m Project Commenced: June 2020 Project Completed: June 2021 Client: Breheny   About the Project This scheme involves the construction of 2 no. overbridges for our client Breheny. The first bridge is a 17m span, prestressed concrete overbridge spanning a road. The second bridge is a 30m span, prestressed concrete overbridge spanning a railway which required an 800T crane to install the deck beams. The bridges were critical activities…

East Croydon MDU

Civils Design Professional Services Surveys

Client: Network Rail Programme: 3 Months (September 2020)   Objective: The overall objective for the scheme was to undertake a Feasibility Study for Network Rail. The work included multi-discipline surveys for the site, including PAS128 Surveys and develop options to upgrade the existing Network Rail office accommodation in line with client requirements. Key considerations for…